Process flow: drill in place → Drilling → Mud injection → Run casing → Continue drilling → Slag removal → Hole cleaning → Hoist the reinforcement cage → Water jetting and bottom cleaning → Concrete conduit → Placing concrete → Catheter & rarr; The pile top reinforcement can be divided into single liquid silicification method, double liquid silicification method, aerated silicification method and electric double liquid silicification method.Repetitive grouting pipe can be reused for many times. Long term grouting steel flower pipe, steel flower pipe grouting, pile foundation grouting pipe, grouting pipe manufacturer, old brand, price advantage and quality! Each time it is used up, the pipe core and the outer wall of the pipe shall be washed clean.
According to the sequence of sectional construction along the stratum depth, grouting can be divided into sectional downward, sectional upward and sub full depth grouting. The segmented downward type is to start from the ground, continue to extend the drilling and grouting, and then carry out re grouting from bottom to top; The sectional upward pattern is that the grouting hole is drilled to the final grouting depth at one time. All kinds of grouting pipes, steel flower pipes, advance small conduits, high-pressure grouting pipes, pipe shed pipes and the formal qualification of grouting pipe factory are welcome to inquire by telephone and sincerely invite cooperation! Grout stop shall be used for bottom-up sectional grouting; The secondary full depth grouting method is to drill the grouting hole to the final grouting depth, and then conduct secondary grouting for the full depth.The grouting equipment, grouting pump and the lowered grouting pipe are connected for grouting, and the grouting is carried out according to the requirements. The grouting pump will inject the slurry into the soil. After completing the construction of one grouting section move the grouting pipe up or down according to the requirements to carry out the construction of the next grouting section.BeukarGrouting pipeLong and short factors are intertwined, and the price is difficult to figure out,2022-06-2309:59:38Process flow: drill in place → Drilling → Mud injection → Run casing → Continue drilling → Slag removal → Hole cleaning → Hoist the reinforcement cage → Water jetting and bottom cleaning → Concrete conduit → Placing concrete → Catheter & rarr; The pile top reinforcement can be divided into single liquid silicification method, double liquid silicification method, aerated silicification method and electric double liquid silicification method.The secondary grouting pipe can only be grouted once and cannot be reused.
support 0 | be opposed to 0